Comparison
What does a kilowatt hour cost in winter?
Every technology delivers part of its power in winter and part in summer. Here, the winter kWh carry the full cost. Solar power counts for nothing in summer. Power from nuclear and wind, which flows around the clock, counts for 4 centimes in summer.


The bar shows the range from cheap to expensive assumptions, the line the middle one.
Assumptions: lifetime of 30 years for solar, 20 years for batteries, 60 years for nuclear. Real interest rate of 2 to 5 percent, 3 to 7 percent for nuclear. Nuclear construction costs of 6’000 to 16’000 CHF per kW, construction time of 8 to 15 years. All values and sources on the page Assumptions and sources.
New nuclear plant: cheap on paper, but risky
With the construction costs from the BAK Economics study for economiesuisse (the Swiss business federation), a winter kWh costs around 19 centimes.29 With costs like those of Britain’s Hinkley Point C, it is over 50 centimes.31 It would deliver power in 2045 at the earliest, more likely 2050.32
Wind: the cheapest new winter source
Around 22 centimes per winter kWh. But permits today often take ten years or more.
Solar on the Swiss Plateau: expensive for winter, but available now
As overcapacity together with wind and storage lakes, it closes the gap, without decades of construction and without the cost risk of a large project.
Seasonal battery: ruled out
Each kilowatt hour from it costs more than 50 times as much as from any other solution.
The cheapest is what already exists
Running Gösgen and Leibstadt for 80 instead of 60 years costs the least. The Federal Council considers this technically feasible.28 But it only postpones the question by 20 years.
| Scenario 2050 | Imports in winter | Surplus per year | Cost per year | per kWh | Available |
|---|---|---|---|---|---|
| 2050 under the Electricity Act, without nuclear | 5.5 TWh (above guideline) | 19.8 TWh | 4.9 bn CHF | 7.2 ct. | step by step until 2050 |
| Solar deliberately oversized | 0.0 TWh | 35.4 TWh | 7.3 bn CHF | 10.6 ct. | step by step until 2050 |
| Renewable mix with more wind | 0.0 TWh | 28.1 TWh | 6.2 bn CHF | 9.0 ct. | step by step until 2050, permits for wind difficult |
| Store the summer in batteries | 0.0 TWh | 13.1 TWh | 119.4 bn CHF | 173.8 ct. | battery technically available now |
| A new nuclear plant from 2050 | 0.0 TWh | 26.8 TWh | 5.7 bn CHF | 8.4 ct. | nuclear plant in 2045 at the earliest, more likely 2050 |
| Gösgen and Leibstadt run for 80 years | 0.0 TWh | 31.5 TWh | 5.1 bn CHF | 7.4 ct. | running beyond 60 years requires approval |
Cost per year: new solar plants and wind turbines, battery, nuclear plants and imported power, at today’s prices. Existing hydropower, the grid and levies are not included, because they are the same in all scenarios. Surplus: power that has to be exported or curtailed.